This content is restricted to site members. If you are an existing user, please log in. New users may register below.
Tender Process – Action of imposing the penalty without putting notice to party cannot be approved.
Bysclaw
Apr 23, 2023By sclaw
Related Post
Coal Mining Bid — Rejection of — Eligibility criteria — Appellants challenged the rejection of its technical bid by Respondent-BCCL for a coal mining project, while the bid of Respondent No. 8 was accepted despite non-compliance with mandatory requirements —Whether BCCL was justified in rejecting the appellant’s bid and accepting the bid of Respondent No. 8, which did not meet the eligibility criteria — Appellant argues that the rejection was arbitrary and discriminatory — The appellant complied with all requirements, while Respondent No. 8 was allowed to submit missing documents later — BCCL argues that the appellant’s bid was non-compliant due to issues with the Power of Attorney — The Tender Committee could seek shortfall documents but not replace them —The Supreme Court found BCCL’s actions arbitrary and illegal, setting aside the rejection of the appellant’s bid and the acceptance of Respondent No. 8’s bid — The appellant’s Power of Attorney was valid and notarized before submission — BCCL’s acceptance of Respondent No. 8’s bid despite non-compliance was unjustified —Government bodies must act fairly and transparently in awarding contracts — The decision-making process must be free from arbitrariness and bias —The Supreme Court allowed the appeal, setting aside BCCL’s decision and any subsequent agreements, and directed BCCL to initiate a fresh tender process.
Oct 9, 2024
sclaw
Power Purchase Agreement (PPA) — PPA between Bangalore Electricity Supply Company Limited, and the Hirehalli Solar Power Project LLP — The respondent sought an extension of the scheduled commissioning date (SCD) under the force majeure clause of the PPA due to delays in obtaining necessary approvals and licenses —The Karnataka Electricity Regulatory Commission (KERC) rejected the force majeure claim, but the Appellate Tribunal for Electricity (APTEL) reversed the decision, finding that the delay was not attributable to the respondent and that the force majeure clause was applicable — The Supreme Court agreed with the APTEL’s findings and dismissed the appeals — The court also rejected the appellant’s contention that the APTEL’s direction to pay late payment surcharge to the respondent was unjustified, as it was rooted in the PPA and in furtherance of the intention of the parties.
Aug 29, 2024
sclaw
National Highways Act, 1956 — National Highways Fee (Determination of Rates and Collection) Rules, 2008 — The Court concluded that it would be impossible to return the collected toll/fee to the road users, and any order modifying the interim order would be detrimental and harmful to the road users as additional amounts would have to be collected to make up for the cost of the highway — Therefore, the Court allowed the present appeal and set aside the judgment of the High Court — The Court also directed that the amount lying deposited in the nationalized bank along with interest may now be utilized by NHAI and would be treated as toll/fee collected from the users, and it would be accounted towards the actual cost to be recovered.
Aug 18, 2024
sclaw